File #: 24-1021    Version: 1 Name:
Type: Action Item Status: Passed
File created: 7/8/2024 In control: Board of Public Works
On agenda: 7/15/2024 Final action:
Title: Consideration of award of contract for City Contract 24-91, WISDOT Project ID 2994-08-70, C Wauwatosa Lighting Conversion, Various Streets, Projects 2403 and 2405
Sponsors: Engineering, Michael Steiner
Attachments: 1. Resolution
Related files: 24-1059
title
Consideration of award of contract for City Contract 24-91, WISDOT Project ID 2994-08-70, C Wauwatosa Lighting Conversion, Various Streets, Projects 2403 and 2405

body
Submitted by:
Mike Steiner, P.E., Assistant City Engineer
Department
Public Works, Engineering Division

A. Issue
Award of City Contract 24-91, WISDOT Project ID 2994-08-70, C Wauwatosa Lighting Conversion, Various Streets, Projects 2403 and 2405


B. Background/Options
We have examined the five bids submitted for City Contract 24-91, WISDOT Project ID 2994-08-70, C Wauwatosa Lighting Conversion, Various Streets, Projects 2403 and 2405 on Thursday, July 11, 2024.

The City has been replacing high pressure sodium (HPS) street light fixtures with energy efficient LED street light fixtures over the past five years. The City applied for and received funding through a federal grant program, Carbon Reduction Program (CRP), to continue this effort. This contract includes replacing approximately 450 street light fixtures throughout the City on arterial roadways and in City parking lots.

The contract also replaces 170 fixtures within the Washington Highlands Subdivision with decorative fixtures. The increased costs associated with the decorative fixtures will be paid for by the Subdivision through a special assessment process.

The bids received are as follows:
PGS Signal & Lighting $247,733.97
Pro Electric, Inc. $277,865.33
WIL-Surge Electric, Inc. $322,258.00
Van Ert Electric $423,250.00
Outdoor Lighting Const. Co., Inc $471,458.00




C. Strategic Plan (Area of Focus)
Infrastructure


D. Fiscal Impact
This project is being funded with 80% federal funding up to a maximum of $305, 674 for all federally funded project phases through the Carbon Reduction Program. All remaining funds are included in the approved 2024-2028 Capital Budget as Projects 2403 and 2405.


E. Recommendation
We recommend the award be made to PGS Signal & Lighting for their bid price of $247,733.97,...