File #: 24-1535    Version: 1 Name:
Type: Report Status: Information Only
File created: 11/6/2024 In control: Board of Public Works
On agenda: 11/13/2024 Final action: 11/13/2024
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming

Department:

Engineering

 

23-90 - 2023 Fiber

                     Railroad flagging is being coordinated to allow the boring under the railroad to occur.

                     The contractor is looking to install fiber along the Mayfair corridor from North Ave to Madison school area in the next few weeks.

 

23-30 - Wauwatosa Bike Share

                     Work scheduled on the remaining two bike pads within the next week or two.

 

Elm Grove Water Main Extension

                     The next portion of watermain work in Elm Grove is close to dedication.

                     Once dedicated, additional water laterals will be installed and the project will be nearly completed.

 

24-01 - Potter Road & 109th St.

                     Paving is scheduled for next week to be followed by restoration and final prep before construction is paused for the winter.

                     Fine grading occurred last week.

                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

                     Landscaping and work on the playground area are on-going.

                     Site stabilization is also underway in prep for the winter.

 

24-07 - 2024 Street Improvements

                     Lateral grouting is expected to be completed by the end of the week.

                     All other work and punch list is complete.

 

24-19 - 2024 Sidewalk Repair Program

                     Substantially complete and punch list work is underway.

 

24-24 - Concrete Pavement Repairs

                     Substantially complete.

 

24-51 - Mayfair Rd. Water Main Lining

                     Substantially complete, punch list issued.