Project Updates
body
Submitted by:
Nick Deming
Department:
Engineering
23-90 - 2023 Fiber
• Railroad flagging is being coordinated to allow the boring under the railroad to occur.
• The contractor is looking to install fiber along the Mayfair corridor from North Ave to Madison school area in the next few weeks.
23-30 - Wauwatosa Bike Share
• Work scheduled on the remaining two bike pads within the next week or two.
Elm Grove Water Main Extension
• The next portion of watermain work in Elm Grove is close to dedication.
• Once dedicated, additional water laterals will be installed and the project will be nearly completed.
24-01 - Potter Road & 109th St.
• Paving is scheduled for next week to be followed by restoration and final prep before construction is paused for the winter.
• Fine grading occurred last week.
• Work on 109th St. will take place in 2025 based on current progress on the project.
24-02 - 116th St. Park
• Landscaping and work on the playground area are on-going.
• Site stabilization is also underway in prep for the winter.
24-07 - 2024 Street Improvements
• Lateral grouting is expected to be completed by the end of the week.
• All other work and punch list is complete.
24-19 - 2024 Sidewalk Repair Program
• Substantially complete and punch list work is underway.
24-24 - Concrete Pavement Repairs
• Substantially complete.
24-51 - Mayfair Rd. Water Main Lining
• Substantially complete, punch list issued.