Legislation Details

File #: 24-1535    Version: 1 Name:
Type: Report Status: Information Only
File created: 11/6/2024 In control: Board of Public Works
On agenda: 11/13/2024 Final action: 11/13/2024
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming

Department:

Engineering

 

23-90 - 2023 Fiber

•                     Railroad flagging is being coordinated to allow the boring under the railroad to occur.

•                     The contractor is looking to install fiber along the Mayfair corridor from North Ave to Madison school area in the next few weeks.

 

23-30 - Wauwatosa Bike Share

•                     Work scheduled on the remaining two bike pads within the next week or two.

 

Elm Grove Water Main Extension

•                     The next portion of watermain work in Elm Grove is close to dedication.

•                     Once dedicated, additional water laterals will be installed and the project will be nearly completed.

 

24-01 - Potter Road & 109th St.

•                     Paving is scheduled for next week to be followed by restoration and final prep before construction is paused for the winter.

•                     Fine grading occurred last week.

•                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

•                     Landscaping and work on the playground area are on-going.

•                     Site stabilization is also underway in prep for the winter.

 

24-07 - 2024 Street Improvements

•                     Lateral grouting is expected to be completed by the end of the week.

•                     All other work and punch list is complete.

 

24-19 - 2024 Sidewalk Repair Program

•                     Substantially complete and punch list work is underway.

 

24-24 - Concrete Pavement Repairs

•                     Substantially complete.

 

24-51 - Mayfair Rd. Water Main Lining

•                     Substantially complete, punch list issued.