title
Project Updates
body
Submitted by:
Nick Deming
Department:
Engineering
22-05 - 103rd St. Storm Sewer Relay
• Light poles are installed. Project is substantially complete.
Project 1107 - North Avenue Reconstruction
• WB Traffic was shifted last week to the north for the rest of the project east of 103rd St.
• Median work is on-going throughout the project with the majority of work remaining at the east end. Curb and gutter is scheduled to be placed starting last week and running into the week of 11/20
• Permanent street lighting was started to be installed last week.
• Pavement marking is scheduled to start the week of 11/20 in areas available throughout the project.
• The remainder of the paving work is currently scheduled for the week of 11/27.
23-07 - 115th St.
• Awaiting delivery of backordered light poles.
• Punch list was issued to the contractor.
23-90 - 2023 Fiber
• Handhole installation is ongoing. This work is located throughout the City.
Elm Grove Water Main Extension
• The contractor is wrapping up installation of the water main planned to be installed in 2023. The remaining water main in the neighborhood south of Watertown Plank will resume when weather breaks in 2024.
• The City is awaiting a road restoration schedule from the contractor.