title
Project Updates
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering Division
Project 1107 - North Avenue Reconstruction
• Punch list work and final landscaping to resume in Spring 2024.
23-07 - 115th St.
• Awaiting delivery of backordered light poles. Installation is expected to take place once poles are available in winter of 2024.
23-90 - 2023 Fiber
• Work is expected to resume in Spring of 2024.
Elm Grove Water Main Extension
• The remaining water main work is expected to resume in Spring of 2024.