Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering Division

 

Project 1107 - North Avenue Reconstruction

                     Punch list work and final landscaping to resume in Spring 2024.

 

23-07 - 115th St.

                     Awaiting delivery of backordered light poles.  Installation is expected to take place once poles are available in winter of 2024.

 

23-90 - 2023 Fiber

                     Work is expected to resume in Spring of 2024.

 

Elm Grove Water Main Extension

                     The remaining water main work is expected to resume in Spring of 2024.