Title: Approval of Final Payment for Contract 22-25, Project 2304 Tosa Trails, Webster Park Connection
Attachments: 1. 22-25 Final Signed
Related files: 24-0476

title
Approval of Final Payment for Contract 22-25, Project 2304 Tosa Trails, Webster Park Connection

 

body

Dear Board Members:

 

Payne & Dolan, Inc. has completed the work of the Tosa Trails, Webster Park Connection and work incidental thereto under Contract 22-25 / Project 2304.  The work took place in Webster Park to create a connection between the parking area and the Oak Leaf Trail.

 

The final contract value is $80,127.40. The contract award amount was $62,069.75.  The final amount due the contractor is $18,800.15.  There were no change orders issued on the project.

 

I hereby certify that the work on Contract 22-25 / Project 2304 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.

 

Sincerely,

 

Nick Deming, PE

Construction Manager

 

 

By: Board of Public Works

 