File #: 26-0353    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 2/11/2026 In control: Board of Public Works
On agenda: 2/18/2026 Final action:
Title: Project Updates
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Project Updates

 

body

23-90 - 2023 Fiber

                     Awaiting DOT approval on revised permit.

 

25-01 - Wisconsin Avenue

                     Roadway work complete for winter at 76th St. Permanent sidewalks to be installed in Spring ’26.

                     Signals are installed and operational.

 

25-07 - Watertown Plank Road

                     Contractor has shut down for winter. Work to resume in late Winter/early Spring ’26.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

                     Permanent restoration to be completed in Spring ’26.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.