File #: 24-0340    Version: 1 Name:
Type: Report Status: Information Only
File created: 2/27/2024 In control: Board of Public Works
On agenda: 3/18/2024 Final action: 3/18/2024
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming

Department:

Engineering

 

Project 1107 - North Avenue Reconstruction

                     Punch list work and final landscaping to resume in spring.  Awaiting the Spring schedule from the Contractor.

 

23-07 - 115th St.

                     Electrical work is completed.  Restoration work around the electrical work install over winter will occur later this spring.

 

23-90 - 2023 Fiber

                     Work is expected to resume in spring.  Some handhole installation work may take places as weather allows through the winter.

 

Elm Grove Water Main Extension

                     The remaining water main work is expected to resume in late March.

 

24-01 - Potter Road & 109th St.

                     The Preconstruction Meeting was held on Wednesday, 3/13.

                     Potter Road, 109th St., and the Oak Leaf Trail are scheduled to close for project work beginning on March 25th  to mobilize in equipment and prep the site for work to begin.

                     Sanitary Sewer work is expected to start late the week of March 25th or the week of April 1st.

 

24-19 - 2024 Sidewalk Repair Program

                     The Preconstruction Meeting is scheduled for Thursday, 3/28.

                     Work is expected to begin on pedestrian ramps in early to mid April.

 

24-43 - Highlands Railing Replacement

                     Contracts are executed.

                     A request was sent to the contractor regarding scheduling a Preconstruction Meeting and the project schedule.