title
Project Updates
body
Submitted by:
Nick Deming
Department:
Engineering
Project 1107 - North Avenue Reconstruction
• Punch list work and final landscaping to resume in spring. Awaiting the Spring schedule from the Contractor.
23-07 - 115th St.
• Electrical work is completed. Restoration work around the electrical work install over winter will occur later this spring.
23-90 - 2023 Fiber
• Work is expected to resume in spring. Some handhole installation work may take places as weather allows through the winter.
Elm Grove Water Main Extension
• The remaining water main work is expected to resume in late March.
24-01 - Potter Road & 109th St.
• The Preconstruction Meeting was held on Wednesday, 3/13.
• Potter Road, 109th St., and the Oak Leaf Trail are scheduled to close for project work beginning on March 25th to mobilize in equipment and prep the site for work to begin.
• Sanitary Sewer work is expected to start late the week of March 25th or the week of April 1st.
24-19 - 2024 Sidewalk Repair Program
• The Preconstruction Meeting is scheduled for Thursday, 3/28.
• Work is expected to begin on pedestrian ramps in early to mid April.
24-43 - Highlands Railing Replacement
• Contracts are executed.
• A request was sent to the contractor regarding scheduling a Preconstruction Meeting and the project schedule.