File #: 25-0613    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 4/10/2025 In control: Board of Public Works
On agenda: 4/16/2025 Final action:
Title: Project Updates
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Project Updates

 

body

23-90 - 2023 Fiber

                     The contractor is looking to start pulling fiber in the next few weeks once the WisDOT permit extension is received.

 

Elm Grove Water Main Extension

                     The remaining water main has been dedicated to the City of Wauwatosa

                     Additional lateral work is scheduled to resume in the next few weeks.

 

24-01 - Potter Road & 109th St.

                     Sanitary sewer and water are installed on 109th with some connections and laterals to be completed as the storm sewer is installed.

                     Storm sewer is underway with the mainline installed up to Wells St. Storm is expected to continue over the next few weeks.

 

24-02 - 116th St. Park

                     Work on the retaining wall on the south end of the project is nearly complete.

                     Paving of the paths is scheduled for late April.

                     Restoration is on-going throughout the site area.

                     The restroom is installed

 

25-01 - Wisconsin Avenue

                     The contractor is currently working on installation of water along Wisconsin Avenue between 68th St. and 72nd St. This work is expected to continue over the next couple of weeks.

 

25-07 - Watertown Plank Road

                     Tree Clearing on county grounds is complete. The trees were laid on-site and will be cleaned up in the next couple of weeks.

                     Work is expected to start with traffic control and utilities near the end of April or Early May.

 

25-19 - 2025 Sidewalk Program

                     A preconstruction meeting is scheduled for April 22nd.

                     Work is expected to start with saw cutting curb ramp replacement areas in late April/early May with removals starting in mid May.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     The preconstruction meeting was held and work is expected to begin in the next couple of weeks to prep and demolish the existing bridge.

                     The road remains closed at the project site after WE Energies gas completed there work to remove abandoned gas mains.