title
Approval of Final Payment for Contract 22-05 N 103rd St Storm Sewer Relay
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering Division
Dear Board Members:
Globe Contractors, Inc. has completed the work of the 103rd St. Storm Sewer Improvements project and work incidental thereto under Contract 22-05 / Project 4102. The work took place on N. 103rd St. between W. North Avenue and W. Wright St.
The final contract value due to the contractor is $2,550,636.63. The contract award amount was $2,647,187.00. The final amount due to the contractor is $146,040.83. There was one change order on the contract that addressed a remobilization of equipment due to a scope change after work was complete and two emergency repairs to the storm sewer system outside of the project limits.
I hereby certify that the work on Contract 22-05 / Project 4102 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Nick Deming, PE
recommendation
Recommendation: Common Council