title
Consideration of a request by Mariana Arena, Engberg Anderson Architects, for Planned Unit Development final plans at 11220 W. Burleigh Street for a multi-unit building (The Foundry)
body
Submitted by:
Tamara Szudy
Department:
Development
A. Background/Options
In 2011, the City granted approval of a Preliminary Planned Unit Development (PUD) for the Mayfair Collection mixed-use development at the northeast corner of Burleigh Street and I-41. The project anticipated the development of retail, hospitality, restaurants, office, and high-density housing on the approximate 70-acre site. Since 2011, Final PUD approvals have been granted for portions of the project area and the Mayfair Collection has transitioned into a vibrant, regional shopping and dining destination.
In January 2023, the City approved a Final PUD for Phase 1 of The Foundry housing development, consisting of two five-story, mixed-use buildings containing 289 residential units and an underground basement with 672 stalls and long-term bicycle parking.
The applicant is now proposing a Final PUD for Phase 2 of The Foundry which consists of two five-story multi-family buildings containing 234 units, underground parking with 688 stalls, and landscape terraces between buildings. Project amenities will be shared with Phase 1 of the development and include a pool, gym, grilling areas, dog park, and social gathering spaces. Multi-modal pathways and public open spaces are also incorporated.
Final PUD plans are reviewed for compliance with conditions placed on the Preliminary PUD approval from 2011. The Preliminary PUD approval for the Mayfair Collection contemplated multi-family housing in this location. The resolution and preliminary information is attached. Some preliminary approval conditions are recommended for placement on the final approval as they relate to subsequent approvals and/or requirements necessary to obtain other permits:
1. Plans showing adequate sewer capacity, environmental re...