title
Request by the Engineering Division for approval of plans and specifications for Contract 25-07 / Project 1025, W. Watertown Plank Road and N. 115th Street Utilities and Paving. Project limits on W. Watertown Plank Road are N. 113th Street to N. 124th Street. Project limits on N. 115th Street are Walnut Road to Underwood Parkway.
body
Submitted by:
Chris Jain, P.E., Senior Civil Engineer
Department:
Public Works, Engineering Division
A. Issue
Request by the Engineering Division for approval of plans and specifications for Contract 25-07 / Project 1025, W. Watertown Plank Road and N. 115th Street Utilities and Paving
B. Background/Options
Engineering has prepared the attached plans and specifications for sanitary sewer, water main, storm sewer, roadway and pedestrian facilities, street lighting, communications, and traffic signal improvements within the project limits. The work is planned to begin in April 2025 and conclude in August 2026.
C. Strategic Plan (Area of Focus)
Priority 2: Public Safety, Goal 2 - Proactively address pedestrian, bicycle and vehicular safety.
Priority 3: Infrastructure, Goal 1 - Optimize infrastructure to handle 100-year storm events.
Priority 3: Infrastructure, Goal 2 - Ensure the City’s infrastructure supports public health through multi-modal transportation and recreation opportunities.
D. Fiscal Impact
The project is included in the approved 2025-2029 Capital Budget.
E. Recommendation
Staff recommends approval of the plans and specifications and authorization be granted to the City Clerk to advertise for bids on Contract 25-07/Project 1025, W. Watertown Plank Road and N. 115th Street Utilities and Paving.