title
Consideration of award of Contract 25-08 / Project 1024, Center Street Improvements to MJ Construction, Inc. in the amount of $1,414,080.00
body
Submitted by:
Jeni Schroeder, PE
Department
Department of Public Works - Engineering Services
A. Issue
Consideration of award of Contract 25-08 / Project 1024, Center Street Improvements to MJ Construction, Inc. in the amount of $1,414,080.00.
B. Background/Options
The project consists of sanitary sewer lateral, water main, storm sewer leads and inlets, roadway and pedestrian facilities and communications improvements within the project limits.
Project limits are on Center Street from N. 113th Street to N. 118th Street. The project will complete the road work that was associated with the underground utility installations in the summer of 2024. The western driveway entrance to the schools will be realigned to match into the intersection with N. 116th Street. The work is planned for the 2025 construction season.
We have examined the three (3) bids submitted for Contract 25-08 / Project 1024, Center Street Improvements on Wednesday, March 5, 2025. The bids received are as follows:
MJ Construction $1,414,080.00
Mid City Corporation $1,473,160.92
LaLonde Contractors, Inc. $1,586,931.88
C. Strategic Plan (Area of Focus)
Priority 2: Public Safety, Goal 2 - Proactively address pedestrian, bicycle and vehicular safety.
Priority 3: Infrastructure, Goal 1 - Optimize infrastructure to handle 100-year storm events.
Priority 3: Infrastructure, Goal 2 - Ensure the City's infrastructure supports public health through multi-modal transportation and recreation opportunities.
D. Fiscal Impact
The project was included in the approved 2024-2028 Capital Budget. An estimated $125,000 of the project cost will be reimbursed by the Wauwatosa School District.
E. Recommendation
Staff recommends the award be made to MJ Construction, Inc. and for their bid price of $1,414,080.00, this being the lowest a...
Click here for full text