Request by Ainae Schmaus of Cornerstone One, LLC for construction staging within the Blanchard Street right-of-way adjacent to the Harlow and Hem development at 7470 Blanchard Street
body
Submitted by:
Jennifer Stilling, Senior Civil Engineer
Department:
Public Works (Engineering Services)
Issue
The applicant has requested a 23-day Blanchard Street full road closure adjacent to the proposed Harlow and Hem development at 7470 Blanchard Street for utility installation and abandonments.
Background/Options
As shown in the attached traffic control plan, the applicant is proposing a full Blanchard Street closure directly adjacent to the proposed Harlow and Hem development. The full road closure is necessary for the installation of water, sewer, and storm laterals for the development along with required lateral abandonments. A full road closure is also necessary based on the location of the public mains and to provide a safe working area for the construction crews.
The proposed work will be split into two phases. Phase 1 proposes that Blanchard Street is closed from Wauwatosa Avenue to just west of the State Street Station parking garage entrance/exit. Local traffic will be allowed to access Blanchard Street from the east and access to State Street Station parking garage will not be impacted. This phase of work will have a duration of approximately 9 days.
Phase 2 proposes that Blanchard Street is closed directly adjacent to the former residential property at 7462 Blanchard Street as shown in the attached exhibit. Local traffic will be allowed to use Blanchard Street but one of the State Street Station structured parking exits may have limited access. This phase of work will have a duration of approximately 14 days.
In general, the proposed work hours are 7 am to 7 pm. Blanchard Street will be open and accessible at night with the use of road plates, except for during the pavement restoration phase during Phase 2. The road will need to remai...