title
Approval of plans and specifications for Contract 26-19, Sidewalk Repair Program, in an area largely bounded by North Ave. to the south, 88th St. to the west, Center St. to the north and Lefeber Ave. to the east.
body
Submitted by:
Jeni Schroeder, PE
Senior Civil Engineer
Department:
DPW, Engineering
A. Issue
Engineering is requesting approval of plans and specifications for City Contract 26-19.
B. Background/Options
Engineering has prepared the attached the Sidewalk Repair Program plans and specifications. The 2026 sidewalk repair area, is largely bounded by North Ave. to the south, 88th St. to the west, Center St. to the north and Lefeber Ave. to the east. This contract also includes rehabilitating hazardous curb ramps within Hart Park. The work includes 1,300+ squares, 16 curb ramp reconstructions within the repair area and 15 curb ramp reconstructions within Hart Park.
C. Strategic Plan (Area of Focus)
Priority 2: Public Safety, Goal 2 - Proactively address pedestrian, bicycle and vehicular safety.
Priority 3: Infrastructure, Goal 2 - Ensure the City’s infrastructure supports public health through multi-modal transportation and recreation opportunities.
D. Fiscal Impact
Project has been included in the proposed 2026-2030 Capital Budget.
E. Recommendation
Staff recommends approval of the plans and specifications and authorization be granted to the City Clerk to advertise for bids on Contract 26-19, Sidewalk Repair Program.