Submitted by:
Nick Deming, Construction Manager
Department:
Engineering
Project 1107 - North Avenue Reconstruction
• The contractor has the outside lanes close on North Avenue to complete repairs in the outside lanes and terrace areas.
• In a week or two, it is expected the contractor will move traffic to the outside lanes to begin repairs in the median.
• Tree planting is underway also.
23-90 - 2023 Fiber
• Work is continuing with handhole installation.
23-30 - Wauwatosa Bike Share
• Work to resume in fall in coordination with MRMC and the site work that is on-going.
Elm Grove Water Main Extension
• Water main work in Elm Grove is underway.
24-01 - Potter Road & 109th St.
• Sanitary sewer main line work on Potter is expected to wrap up early the week of 4/29
• Storm sewer work is expected to start immediately following the sanitary mainline work. Work will start near Underwood Creek at the outfall.
24-02 - 116th St. Park
• Preconstruction Meeting Date TBD
24-07 - 2024 Street Improvements
• Preconstruction Meeting Date TBD
24-11 - Green Alleys
• Work is expected to start the week of May 6th with pavement repair along the side streets on 124th between Center St. and Burleigh Ave.
24-19 - 2024 Sidewalk Repair Program
• Ramp removal and replacement is on-going and expected to continue the next couple of weeks.
24-43 - Highlands Railing Replacement
• Bridge repair work to begin the week of 4/29.
• Rail replacement slated for early June.
WisDOT Zoo IC North Leg
• Swan Blvd. from Discovery Parkway west to Underwood Parkway is closed for concrete repairs. Duration is expected to be about 1 month.