title
Consideration of a State/Municipal Agreement with the Wisconsin Department of Transportation for the repaving of Glenview Ave (STH 181) between Blue Mound Road and south city limits (CIP 1123)
body
Submitted by:
Bill Wehrley, City Engineer
Department
Public Works - Engineering Division
A. Issue
Approve a State Municipal Agreement (SMA) with the Wisconsin Department of Transportation (WisDOT) for City costs associated with the repaving of Glenview Ave (STH 181) between Blue Mound Road and south city limits (CIP 1123).
B. Background/Options
The DOT will be repaving portions of Blue Mound Road (USH 18) and Glenview Avenue (STH 181) in 2028 or 2029. Last year we approved an SMA with WisDOT for the Blue Mound Road portion of this project (Common Council Resolution Res-23-16). The DOT has separated out the repaving of Glenview Avenue into its own project. As such, attached is a separate SMA for Glenview Avenue repaving.
As this is a connecting highway there will be significant State and/or Federal dollars to offset much of the construction cost. Portions of this project are within the City of Milwaukee.
Design is anticipated to take several years and construction is anticipated to occur in 2028 or 2029 subject to future DOT schedule changes.
C. Strategic Plan (Area of Focus)
Priority 2: Public Safety Goal 2, Proactively address pedestrian, bicycle, and vehicle safety.
Priority 3: Infrastructure, Goal 2, Ensure the City's infrastructure supports public health through multimodal transportation and recreational opportunities.
D. Fiscal Impact
The total estimated cost of the Glenview Avenue project is $1,860,000. The cost for the City-funded paving items is estimated at $91,100. Funding for our share of the project design was included in the 2023 Capital Improvements Plan (CIP project 1123). Funding for our share of construction will be included in the 2028 or 2029 CIP. Final costs will be determined by final design and bid prices.
E. Recommendation
...
Click here for full text