titleConsideration of ratification of project partial payments for work completed pursuant to the terms of the contract
body
BE IT RESOLVED, By the Board of Public Works of the City of Wauwatosa, Wisconsin that the proper City Officers be and they are hereby authorized and directed to issue City orders in favor of the contractor listed below in the amount listed in the column headed “Amount” as partial payment for work completed pursuant to the terms of the contract noted.
Contractor: Milwaukee General Construction Company
Payment No.: 1
Contract/Project No.: 325000010/25-11 Harvard Alley
Amount: $171,044.85
Contractor: Guelig Waste Removal & Demolition LLC
Contract/Project No.: 32500017/24-61
Amount: $165,000.00