title
Project Updates
body
Submitted by:
Nick Deming
Department:
Engineering
21-47/48 Zoo Interchange North Leg (WisDOT Project)
• The entrance and exits at North Avenue to/from NB & SB I41 are expected to reopen on Sunday morning, 11/5. With these ramp openings, the lane closures at the freeway overpasses at North Avenue are expected to reopen also.
• By Sunday, 11/12, the lane closures on Mayfair Road are expected to reopen to all lanes at the freeway.
• Overnight work is scheduled to continue over the next couple of weeks for various work on the freeway and local streets.
22-05 - 103rd St. Storm Sewer Relay
• Backordered light poles were began being installed last week.
Project 1107 - North Avenue Reconstruction
• WB Traffic was placed on the north side of the road west of 103rd St.
• Median work is scheduled to wrap up near the end of the week of 11/6 between Mayfair Rd and 104th St.
• Paving work is scheduled to start the week of 11/6 east of 103rd St. and traffic is expected to be moved shortly after paving is complete.
• Work in the median east of 103rd St. is planned to start right after traffic is moved to the WB outside lanes.
23-07 - 115th St.
• Awaiting delivery of backordered light poles.
23-24 - 2023 Pavement Repair and Spot Improvements
• This project is substantially complete.
23-90 - 2023 Fiber
• Handhole installation is ongoing. This work is located throughout the City.
Elm Grove Water Main Extension
• The contractor is wrapping up installation of the water main planned to be installed in 2023. The remaining water main in the neighborhood south of Watertown Plank will resume when weather breaks in 2024.
• Road restoration work is scheduled to begin mid to late the week of 11/6.