Legislation Details

File #: 26-0567    Version: 1 Name:
Type: Report Status: Information Only
File created: 3/13/2026 In control: Board of Public Works
On agenda: 3/18/2026 Final action: 3/18/2026
Title: Project Updates

title
Project Updates

 

body

23-90 - 2023 Fiber

•                     Awaiting schedule on wrap up work and interior building work.

 

25-01 - Wisconsin Avenue

•                     Awaiting schedule on sidewalk work at 76th St. and Wisconsin Ave.

 

25-07 - Watertown Plank Road

•                     Work to resume on Watertown Plank Road the week of 3/16 with grading work for sidewalk, driveways and roadway.

•                     The week of 3/23 is scheduled to have concrete work on sidewalk, driveways and the roadway.

•                     Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

•                     Permanent restoration to be completed in Spring ’26.

 

25-25 - Burleigh St. Path and Asphalt Repair

•                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.

 

26-01 - Flood Damage Maintenance Repairs

•                     Preconstruction meeting was held on 3/9. Work to start the week of 3/23 in Hart Park with removals and grading.

•                     Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.

 

26-19 - Sidewalk Repair Program

•                     Preconstruction meeting held on 3/9. Work to start the week of 4/1 in Hart Park

 

Hart Park Field Repairs

Awaiting start date from the contractor.

 

Wisconsin Avenue Bridge (WisDOT Led)

•                     Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.