title
Project Updates
body
23-90 - 2023 Fiber
• Awaiting schedule on wrap up work and interior building work.
25-01 - Wisconsin Avenue
• Awaiting schedule on sidewalk work at 76th St. and Wisconsin Ave.
25-07 - Watertown Plank Road
• Work to resume on Watertown Plank Road the week of 3/16 with grading work for sidewalk, driveways and roadway.
• The week of 3/23 is scheduled to have concrete work on sidewalk, driveways and the roadway.
• Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Permanent restoration to be completed in Spring ’26.
25-25 - Burleigh St. Path and Asphalt Repair
• Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.
26-01 - Flood Damage Maintenance Repairs
• Preconstruction meeting was held on 3/9. Work to start the week of 3/23 in Hart Park with removals and grading.
• Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.
26-19 - Sidewalk Repair Program
• Preconstruction meeting held on 3/9. Work to start the week of 4/1 in Hart Park
Hart Park Field Repairs
Awaiting start date from the contractor.
Wisconsin Avenue Bridge (WisDOT Led)
• Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.