Title: Project Updates

title
Project Updates

 

body

23-90 - 2023 Fiber

                     Awaiting schedule on wrap up work and interior building work.

 

25-01 - Wisconsin Avenue

                     Awaiting schedule on sidewalk work at 76th St. and Wisconsin Ave.

 

25-07 - Watertown Plank Road

                     Work to resume on Watertown Plank Road the week of 3/16 with grading work for sidewalk, driveways and roadway.

                     The week of 3/23 is scheduled to have concrete work on sidewalk, driveways and the roadway.

                     Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

                     Permanent restoration to be completed in Spring ’26.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.

 

26-01 - Flood Damage Maintenance Repairs

                     Preconstruction meeting was held on 3/9. Work to start the week of 3/23 in Hart Park with removals and grading.

                     Asphalt work is scheduled for early April but will be dependent on weather and plant reopening after the winter shutdown.

 

26-19 - Sidewalk Repair Program

                     Preconstruction meeting held on 3/9. Work to start the week of 4/1 in Hart Park

 

Hart Park Field Repairs

Awaiting start date from the contractor.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.