File #: 24-1609    Version: 1 Name:
Type: Resolution-Council Status: Passed
File created: 11/13/2024 In control: Common Council
On agenda: 11/19/2024 Final action: 11/19/2024
Title: Resolution declaring the City's intent to perform street and alley improvements during the 2025 construction season and to assess neighboring property owners
Related files: 24-1537
title
Resolution declaring the City's intent to perform street and alley improvements during the 2025 construction season and to assess neighboring property owners

body
BE IT RESOLVED, by the Board of Public Works of the City of Wauwatosa, Wisconsin, that

Section 1. The Board of Public Works of the City of Wauwatosa, Wisconsin hereby declares its intention to exercise its police power, under Section 66.0703 of the Wisconsin Statutes, to levy special assessments upon property in the City of Wauwatosa within the following described area for the benefits conferred upon such property by the repaving of:

Street & Location: N. 115th St. from Underwood Pkwy. to Watertown Plank Rd.
Ald Dist: 3
Exist & Prop. Width: 36 (36)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: No

Street & Location: Watertown Plank Rd. from 113th St. to N. 115th St.
Ald Dist: 3 & 7
Exist & Prop. Width: 52 (52)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: No

Street & Location: Watertown Plank Rd. from 115th St. to N. 124th St.
Ald Dist: 3
Exist & Prop. Width: 52 (52)
Pavement Construction Type: E-Asph
Assessed Sidewalk Work: No

Street & Location: Wisconsin Ave. from N. 68th St. to N. 72nd St.
Ald Dist: 4
Exist & Prop. Width: 40 (40)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: Yes

Street & Location: Alley, Harvard Ln. to Blue Mound Rd. and N. 109th St. to N. 111th St.
Ald Dist: 3
Exist & Prop. Width: 20 (20)
Pavement Construction Type: A-Conc
Assessed Sidewalk Work: No

Section 2. Said public improvement shall include the following work to be done during the 2023 construction season:

Reconstruction: Type "A" (Asph.) or (Conc.) Completely removing existing curb and gutter and existing pavement, placing new concrete curb and gutter (excluding alleys), and asphalt or concrete pavement surface on a new base.


The above repaving type also includes placing necessary water and sewer service pipes and storm sewe...