Title/Recommendation
title
Project Updates
end
Memo Body
body
21-47/48 Zoo Interchange North Leg (WisDOT Project)
• Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.
• Night work is the week of the 31st to remove decking on the bridge over Mayfair Road.
• The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.
22-05 - 103rd St. Storm Sewer Relay
• Restoration work is scheduled to occur in the next week or two.
Project 1107 - North Avenue Reconstruction
• Sidewalk continues being placed on the south side of North Avenue.
• The tree cell installation is on-going for the EB lanes
• Concrete driveways and raised intersections are on the schedule for the next couple of weeks.
• Asphalt paving for both the roadway and the asphalt bike path is projected to start west of 104th in the next two week.
23-07 - 115th St.
• Storm sewer work is underway along 115th St. The contractor is expected to continue to install storm sewer along Potter Rd to 116th St.
• Grading, curb and gutter and pavement is scheduled to be taking place over the next couple of weeks.
23-19 - 2023 Sidewalk Program
• Sidewalk work has moved to primarily to the Research Park area and is expected to wrap up in the next few weeks.
• Restoration work is on-going in other areas.