Title: Project Updates

Title/Recommendation

title

Project Updates

end

Memo Body

body

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

                     Night work is the week of the 31st to remove decking on the bridge over Mayfair Road.

                     The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.

 

22-05 - 103rd St. Storm Sewer Relay

                     Restoration work is scheduled to occur in the next week or two.

 

Project 1107 - North Avenue Reconstruction

                     Sidewalk continues being placed on the south side of North Avenue.

                     The tree cell installation is on-going for the EB lanes

                     Concrete driveways and raised intersections are on the schedule for the next couple of weeks.

                     Asphalt paving for both the roadway and the asphalt bike path is projected to start west of 104th in the next two week.

 

23-07 - 115th St.

                     Storm sewer work is underway along 115th St.  The contractor is expected to continue to install storm sewer along Potter Rd to 116th St.

                     Grading, curb and gutter and pavement is scheduled to be taking place over the next couple of weeks.

 

23-19 - 2023 Sidewalk Program

                     Sidewalk work has moved to primarily to the Research Park area and is expected to wrap up in the next few weeks.

                     Restoration work is on-going in other areas.