Title: Project Updates

Title/Recommendation

title

Project Updates

end

Memo Body

body

21-47/48 Zoo Interchange North Leg (WisDOT Project)

•                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

•                     Night work is the week of the 31st to remove decking on the bridge over Mayfair Road.

•                     The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.

 

22-05 - 103rd St. Storm Sewer Relay

•                     Restoration work is scheduled to occur in the next week or two.

 

Project 1107 - North Avenue Reconstruction

•                     Sidewalk continues being placed on the south side of North Avenue.

•                     The tree cell installation is on-going for the EB lanes

•                     Concrete driveways and raised intersections are on the schedule for the next couple of weeks.

•                     Asphalt paving for both the roadway and the asphalt bike path is projected to start west of 104th in the next two week.

 

23-07 - 115th St.

•                     Storm sewer work is underway along 115th St.  The contractor is expected to continue to install storm sewer along Potter Rd to 116th St.

•                     Grading, curb and gutter and pavement is scheduled to be taking place over the next couple of weeks.

 

23-19 - 2023 Sidewalk Program

•                     Sidewalk work has moved to primarily to the Research Park area and is expected to wrap up in the next few weeks.

•                     Restoration work is on-going in other areas.