File #: 25-0166    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/28/2025 In control: Board of Public Works
On agenda: 2/5/2025 Final action: 2/5/2025
Title: Request by the Engineering Division for approval of plans and specifications for Contract 25-08 / Project 1024, 2025 Center Street Improvements. Project limits are on Center Street from 113th Street to N. 118th Street.
Sponsors: Engineering, Michael Steiner
Attachments: 1. 25-08 Project Manual, 2. 25-08 BPW Plans-1, 3. 25-08_Resolution

title
Request by the Engineering Division for approval of plans and specifications for Contract 25-08 / Project 1024, 2025 Center Street Improvements.  Project limits are on Center Street from 113
th Street to N. 118th Street.

 

body

Submitted by:

Jeni Schroeder, P.E., Senior Civil Engineer

Department:

Public Works, Engineering Division

 

A.                     Issue

Request by the Engineering Division for approval of plans and specifications for Contract 25-08 / Project 1024, 2025 Center Street Improvements.  Project limits are on Center Street from 113th Street to N. 118th Street.

 

B.                     Background/Options 

Engineering has prepared the attached plans and specifications for water main, storm sewer, roadway and pedestrian facilities, and communications within the project limits.  The project will complete the road work that was associated with the underground utility installations in the summer of 2024.  The western driveway entrance to the schools will be realigned to match into the intersection with N. 116th Street.  The work is planned for the 2025 construction season.  

 

 

C.                     Strategic Plan (Area of Focus)

Priority 2: Public Safety, Goal 2 - Proactively address pedestrian, bicycle and vehicular safety.

Priority 3: Infrastructure, Goal 1 - Optimize infrastructure to handle 100-year storm events.

Priority 3: Infrastructure, Goal 2 - Ensure the City’s infrastructure supports public health through multi-modal transportation and recreation opportunities.

 

 

D.                     Fiscal Impact

The project is included in the approved 2025-2029 Capital Budget.

 

 

E.                     Recommendation

Staff recommends approval of the approval of plans and specifications for Contract 25-08 / Project 1024, 2025 Center Street Improvements.