File #: 23-1060    Version: 1 Name:
Type: Action Item Status: Passed
File created: 11/14/2023 In control: Board of Public Works
On agenda: 2/19/2024 Final action: 2/19/2024
Title: Consideration of approval of plans and specifications for Contract 24-11, 2024 Alley Reconstructionn
Attachments: 1. 24-11 Resolution for Plans and Specs, 2. 24-11 Plans, 3. 24-11 Specs

title
Consideration of approval of plans and specifications for Contract 24-11, 2024 Alley Reconstructionn

 

body

Submitted by:

Jennifer Schroeder

Department:

Engineering

 

A.                     Issue

Engineering is requesting approval of plans and specifications for City Contract 24-11, 2024 Alley Reconstruction. Project also includes constructing two accessible parking spots on N. 124th St. and updating curb ramps at three intersections along N. 124th St. under our Pavement Repair Program.

 

B.                     Background/Options 

Engineering has prepared the attached 2024 Alley Reconstruction plans and specifications. 

The work will take place at two alley locations.

 

Alley No. 1

East-West and North-South Legs Between                                                               From:                     N. 122nd St.

Burleigh St. and Chambers St.                                                                                    To:                       N. 124th St.

 

Alley No. 2

Between North Ave. and Meinecke Ave.                                                               From:                     N. 73rd St.

                                                                                                                                                                        To:                      Lefeber Ave

C.                     Strategic Plan (Area of Focus)

Priority Area Three: Infrastructure

- Optimize infrastructure to handle 100-year weather events

- Ensure the City’s infrastructure supports public health through multi-modal transportation and recreation opportunities

 

D.                     Fiscal Impact

Project has been included in the approved 2024-2028 Capital Budget. The stormwater management portions of the two green alleys will be funded by Milwaukee Metropolitan Sewerage District’s Green Solution program.

 

E.                     Recommendation

Staff recommends approval of the plans and specifications and authorization be granted to the City Clerk to advertise for bids on Contract 24-11, 2024 Alley Reconstruction.