title
Request by the Engineering Department for approval of plans and specifications for Contract 24-19, Sidewalk Repair Program
body
Submitted by:
Jennifer Schroeder
Department:
Engineering
A. Issue
Engineering is requesting approval of plans and specifications for City Contract 24-19.
B. Background/Options
Engineering has prepared the attached the Sidewalk Repair Program plans and specifications. The 2024 sidewalk repair area, in general, is largely bounded by IH 94 to the south, 124th St to the west, Hampton Ave to the north and Mayfair Rd/STH 100 to the east. North of Capitol Dr, the project area extends east to 92nd St. The work includes 1,500+ squares, 29 curb ramp reconstructions at various locations and sidewalk extension on Potter Road.
C. Strategic Plan (Area of Focus)
Priority 2: Public Safety, Goal 2 - Proactively address pedestrian, bicycle and vehicular safety.
Priority 3: Infrastructure, Goal 2 - Ensure the City’s infrastructure supports public health through multi-modal transportation and recreation opportunities.
D. Fiscal Impact
Project has been included in the approved 2023-2027 Capital Budget.
E. Recommendation
Staff recommends approval of the plans and specifications and authorization be granted to the City Clerk to advertise for bids on Contract 24-19, Sidewalk Repair Program.