21-47/48 Zoo Interchange North Leg (WisDOT Project)
• Contractor was scheduled to switch traffic into Stage 3 on Wednesday, March 15th.
• Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road.
• The North Leg landscaping contract is awaiting spring planting season to begin work which includes plantings on local streets.
22-05 - 103rd St. Storm Sewer Relay
• Contractor is working on installing water service laterals and relaying sanitary sewer laterals in conflict with the proposed storm sewer.
• The week of 3/20, the contractor is planning to start prepping to install storm sewer starting nearest North Avenue. The first portion (~275’) is within the easement between properties and is expected to continue over the next several weeks.
22-08 - N 68th St.
• Electrical work is pending the arrival of specific materials. The contractor intends to begin installation of these materials once available.
• The new signal poles have been installed over the past couple weeks.
22-60 - DPW Garage Floor Drain Reconstruction
• The resinous flooring in the wash bay is scheduled for installation in April, 2023 when wash out of various vehicles can take place outside until the resinous floor is complete.
Project 1107 - North Avenue Reconstruction
• The contract is being awarded to Vinton Construction. Awaiting contract execution and the scheduling of the preconstruction meeting. Note, this project is being administered by WisDOT.