Skip to main content
File #: 25-0614    Version: 1 Name:
Type: Action Item Status: Passed
File created: 4/10/2025 In control: Board of Public Works
On agenda: 4/16/2025 Final action:
Title: Approval of Final Payment for Contract 23-30 Wauwatosa Bike Share III
Attachments: 1. 23-30 Final Executed, 2. 23-30 Updated Final Board Memo
Related files: 25-0664

title
Approval of Final Payment for Contract 23-30 Wauwatosa Bike Share III

 

body

Submitted by:

Nick Deming

Department:

Engineering

 

Dear Board Members:

 

Zenith Tech Inc. has completed the work of the 2023 Wauwatosa Bike Share III project and work incidental thereto under Contract 23-30 / Project 9961.  The work took place along various locations along N 87th St. and N 92nd St.

 

The final contract value due to the contractor is $66,032.93. The contract award amount was $64,337.30.  The final amount due the contractor is $33,550.75. There was one change order on the contract that addressed remobilization for work completed in the 2024 calendar year that resulted in a net increase in the contract of $4,860.00. The completed contract total due to the contractor was net even with the contract award amount and change order.

 

 

I hereby certify that the work on Contract 23-30 / Project 9961 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.

 

 

Sincerely,

 

Nick Deming, PE

 

 